Federal Court Rejects California Public Utilities Commission’s Re-MAT Program as Non-Compliant with PURPA

Federal Court Rejects California Public Utilities Commission’s Re-MAT Program as Non-Compliant with PURPA

By Buck B. Endemann, William M. Keyser, Molly Suda, and Toks A. Arowojolu

On Wednesday, December 6, 2017, the United States District Court for the Northern District of California (“the Court”) issued a decision in Winding Creek Solar LLC v. Peevey (“Winding Creek decision”),[1] finding that the California Public Utilities Commission’s (“CPUC”) Renewable Market-Adjusting Tariff (“Re-MAT”) program violated the federal Public Utility Regulatory Policies Act (“PURPA”). The Court also found that the CPUC’s “Standard Contract” for generators less than 20 MW failed to comply with PURPA, throwing into question the effectiveness and pricing associated with a significant amount of renewable energy generation currently under contract.