Tag:Large Generator Interconnection Agreement

1
FERC Issues Rule Requiring Wind Generators to Provide Reactive Power as a Condition of Interconnection
2
FERC Proposes Rule That Would Require Wind Generators to Provide Reactive Power as a Condition of Interconnection

FERC Issues Rule Requiring Wind Generators to Provide Reactive Power as a Condition of Interconnection

By Ben Tejblum and William Keyser

On June 16, 2016, the Federal Energy Regulatory Commission (the “Commission”) issued Order No. 827, which establishes reactive power requirements for all new non-synchronous generation (the “Rule”).[1]  Specifically, the Rule revises the Commission’s pro forma Large Generator Interconnection Agreement (“LGIA”) and pro forma  Small Generator Interconnection Agreement (“SGIA”) to require that newly interconnecting non-synchronous generators, including wind generators, provide dynamic reactive power pursuant to the terms of their interconnection agreements.  The Rule is the result of a Notice of Proposed Rulemaking addressing reactive power requirements that was issued by the Commission last November.

Read More

FERC Proposes Rule That Would Require Wind Generators to Provide Reactive Power as a Condition of Interconnection

In a Notice of Proposed Rulemaking issued on November 19, 2015, the Federal Energy Regulatory Commission (the “Commission”) proposed to eliminate the exemption currently available to wind generators from the requirement to provide reactive power.[1] The proposed rule would require that all newly interconnecting synchronous and non-synchronous generators, including wind generators, provide reactive power pursuant to the terms of their interconnection agreements. Additionally, any existing wind generators will be required to provide reactive power if they propose facility upgrades requiring a new interconnection request. Comments on the NOPR are due by the end of January 2016.

Read More