Global Power Law & Policy

Legal and Policy Developments Affecting the Global Power Industry.

 

1
WUTC Investigation Shines the Spotlight on How to Value Energy Storage – Comments Due September 25, 2015
2
EPA’s Clean Power Plan: A Regional Analysis
3
OPUC reschedules Community Solar Workshop 2 for September 22, 2015
4
Eagles Back in the Nest: FWS 30-Year Eagle “Take” Rule Vacated Less than Two Years After Implementation
5
Duke Energy Issues RFPs for Distributed Energy Resource Program
6
OPUC Seeks Public Comment by September 1 in Its Community Solar Program Docket
7
Energy Storage and the Energy Policy Modernization Act
8
Georgia Allows Third Party Ownership (TPO) of Solar
9
Proposals for Community Solar Programs in Oregon due Friday, August 7, 2015
10
EPA releases final version of Clean Power Plan

WUTC Investigation Shines the Spotlight on How to Value Energy Storage – Comments Due September 25, 2015

The Washington Utilities and Transportation Commission (the “WUTC”) is in the midst of an investigation into methods for modeling the costs and benefits of energy storage in utility integrated resource plans (“IRPs”). During its review of the 2013 IRPs of Washington’s regulated utilities (Puget Sound Energy (“PSE”), Avista, and PacifiCorp), the WUTC directed the utilities to start considering how energy storage could be incorporated into future IRPs. As part of this effort, WUTC staff issued a white paper in May 2015: Modeling Energy Storage, Challenges and Opportunities for Washington Utilities. On August 7, the WUTC noticed a comment period on the white paper; the comment period closes on September 25, 2015. The WUTC will use the comments received during this period to determine whether it is necessary to give utilities direction on how energy storage should be treated in their planning and procurement processes, and may issue a policy statement at the end of the investigation to provide that guidance.

Read More

EPA’s Clean Power Plan: A Regional Analysis

EPA’s recently issued Clean Power Plan (“CPP” or “Plan”) affects every state differently. The Plan has a decidedly nationwide impact—reducing the United States’ power plant greenhouse gas emissions 32 percent by the year 2030. But the Plan functions entirely on a state-by-state level, treating each state in a different way based on its unique emissions profile. In this way, the Plan seeks to harness the power of federalism to achieve its ambitious goals.

While the target-based approach is in some ways similar to the structure of EPA’s National Ambient Air Quality Standards (NAAQS), the CPP has revised and reordered certain elements, and has modified the targets for carbon dioxide (CO2) reductions required by individual states. Although NAAQS are set on a nationwide basis, under the CPP every state has a different carbon target based on a calculus that includes the state’s emissions profile and energy mix. Thus, some states (like Montana and West Virginia) are subject to greater emission reductions than other states (like Idaho and Maine). And while states have some flexibility to determine how to meet their targets, the devil will be in the details, as evidenced by EPA’s compliance pathway chart.

Read the full alert on K&L Gates HUB

OPUC reschedules Community Solar Workshop 2 for September 22, 2015

The second workshop in the Oregon Public Utility Commission (the “Commission”) Docket No. UM 1746 (HB 2941 Community Solar Program Design) has been rescheduled from Wednesday, September 23rd to Tuesday, September 22. The workshop was rescheduled in order to accommodate stakeholders who observe Yom Kippur and to encourage stakeholder participation.

Read More

Eagles Back in the Nest: FWS 30-Year Eagle “Take” Rule Vacated Less than Two Years After Implementation

On August 11, 2015, the United States District Court for the Northern District of California struck down a U.S. Fish and Wildlife Service (the “Service”) regulation that increased the maximum duration of programmatic permits for the incidental “take” of bald and golden eagles from five to thirty years (“the 30-Year Rule”)1. The decision sets aside the 30-Year Rule and leaves its fate in the hands of the Service, with potentially negative consequences for those entities that interact with avian resources. Without the 30-Year Rule, entities like wind farms—where avian interaction is effectively unavoidable—face serious questions related to securing permit coverage for their operations and prosecution for incidental take of eagles.

Moreover, until the 30-Year Rule is either reshaped through the administrative process or challenged on appeal, the previous rule—with its five year permit term and need for reapplication/NEPA review every five years—remains in place. Reapplication will trigger administrative burdens for both the permittee and the Service, with respect to both meeting the requirements of NEPA and the potential for appeals.

Read the full alert here on K&L Gates Hub

Duke Energy Issues RFPs for Distributed Energy Resource Program

Duke Energy Carolinas and Duke Energy Progress (collectively, Duke) recently issued two requests for proposals (RFPs) as part of the implementation of Duke’s Distributed Energy Resource Program (DERP). The DERP, which was developed pursuant to South Carolina’s Distributed Energy Resource Act of 2014 (Act 236), was approved by the South Carolina Public Service Commission earlier this year. (See more information about Duke’s program.)

Read More

OPUC Seeks Public Comment by September 1 in Its Community Solar Program Docket

In an email sent to interested stakeholders on August 14, 2015, the Staff of the Oregon Public Utility Commission (the “Commission”) provided further guidance on the public comments due in Docket No. UM 1746 on September 1, 2015, and released a revised docket schedule. As we reported in our August 6, 2015, blog post, the Commission opened UM 1746 to examine a range of possible community solar programs and requested that stakeholders submit proposals for community solar designs by August 7, 2015. Seven stakeholders filed proposals or comments, including Oregon’s investor-owned utilities; Citizens’ Utility Board of Oregon; joint nongovernmental organizations (NWSEED, Oregon SEIA, RNW, Portland Bureau of Planning & Sustainability, Oregonians for Renewable Energy Process, and NWEC); Northwest & Intermountain Power Producers Coalition; Oregon Department of Energy; and Vote Solar. Some of the proposals described specific community solar designs, while others proposed a preferred set of community solar attributes.

Read More

Energy Storage and the Energy Policy Modernization Act

We may be close to seeing the passage of the first major federal energy legislation since the Energy Policy Act of 2007. With a vote of 18-4, the Senate Energy and Natural Resources Committee on July 30, 2015 voted to advance to the Senate floor the Energy Policy Modernization Act. The proposed act was introduced by the leaders of the Senate Energy and Natural Resources Committee: Chairman Lisa Murkowski (R-AK) and ranking member Democrat Maria Cantwell (D-WA). The broad, bipartisan energy legislation is a result of many hearings over 114 proposed energy bills introduced by committee members, dozens of sessions during which stakeholders provided input on the legislation, and over 94 amendments filed during a three-day markup session. The approximately 357-page legislation has five sections: efficiency, infrastructure, supply, accountability, and conservation reauthorization.

Read More

Georgia Allows Third Party Ownership (TPO) of Solar

Recently, Georgia Governor Nathan Deal signed into law House Bill 57, known as the Solar Power Free-Market Financing Act of 2015 (the Solar Power Act). The Solar Power Act, which both houses of the state’s General Assembly passed unanimously, allows homes and businesses to install solar technology under third party ownership (TPO). Although it sailed through the General Assembly, the Solar Power Act is the product of detailed negotiations and compromise between lawmakers, electric service providers, and consumers. The introduction of TPO through the Solar Power Act is expected to provide a significant boost to the residential and commercial solar markets in Georgia. Read More

Proposals for Community Solar Programs in Oregon due Friday, August 7, 2015

Under Section 3 of Oregon’s recently enacted HB 2941, the Oregon Public Utility Commission has opened Docket No. UM 1746 to examine a range of community solar programs that allow individual customers to share in the costs and benefits of solar facilities, focusing on the attributes of different community solar program designs. The Commission is required to submit a recommendation on program design to the legislature by November 1, 2015.

In order to meet the November 1, 2015 deadline, the Commission has created a non-traditional process and accelerated timeline to obtain stakeholder input and finalize the Commission’s recommendation. The Commission has requested that interested parties submit proposals for community solar program designs by this Friday, August 7, 2015, in advance of the first staff workshop scheduled for August 11, 2015. Read More

EPA releases final version of Clean Power Plan

EPA issued the Clean Power Plan in its final form today, August 3, 2015. The rule in effect reshapes energy policy nationwide by setting state-by-state carbon emission standards that all states must achieve through a combination of producing energy more efficiently, reducing energy demand, shifting away from coal-fired generation toward natural gas, nuclear power, and renewable energy, and encouraging state and regional policies such as renewable portfolio standards and cap-and-trade programs. The final rule contains significant changes from the version proposed in 2014, including backing down from an initial earlier deadline for compliance, axing energy efficiency as the fourth “building block” for state targets, increasing the targeted GHG reductions to 32% below 2005 levels by 2030 (up from 30%), and using uniform carbon emissions rates for similar types of power plants.[1]   Read More